Buildings, structure, Infrastructure

        The factory is located on the rectangular plot. It's square is 7 hectares. Distance from the factory to the Danube River is about 350m. The plan of the factory is shown on the picture.

On the plot are located:

  • Tomato shop;
  • Warehouse for products of the tomato shop;
  • Fruit and vegetable canning shop;
  • Warehouse for products of the fruit and vegetable canning shop;
  • Storehouse;
  • Gatekeeper's office with security-fire alarm system room;
  • Transformer substation of the closed type;
  • Building for water preparation;
  • Cooling tower;
  • Boiler-house;
  • Pump.

1. The fruit and vegetable canning shop is built from light metallic constructions such as "Orsk". A size of the shop in the plan is 71,8x24 m, height - 7 m.

Inside the shop there are 2 stored complex of household locations, laboratories, shop pantries, rooms for administrative staff.

Readiness of the object is 70 %.

It is necessary to complete roofing, ventilation system, painting; install equipment.

2. The tomato shop, is built from light metal constructions of the "Kansk" type.

A size of the shop in the plan is 60x24 m., height - 7m.

In proximity to the shop there are reservoirs for tomatoes. From a left-hand side is located a site with two barometric pumps, cooling tower with metal container.

Degree of readiness of the object is 70 %.

3. Warehouses for tomato and fruit and vegetable shops products are built from modular ferro-concrete elements.

A sizes of the shops in the plan: 24x24m, height - 6m.

Degree of readiness is 75 %.

It is necessary to place window blocks, gate, roofing and facing.

4. The material storehouse is built from light metal constructions of an arch type and metalled.

A basement is built from concrete blocks.

Size on the plan is 36x14,4m.

Degree of readiness of warehouses is 75 %

5. The boiler-house is built from modular ferro-concrete constructions. The ferro-concrete frame is mounted in the building of boiler-house, there are no cover, floors, facing, windows, doors, engineering communications. Two boilers DE 6,5-14-GM are installed but not connected.

Readiness degree of boiler-house is 35 %.

6. The walls of the transformer substation are built of bricks, cover is made from modular ferro-concrete plates. 2 400 kWt transformers are installed in the transformer substation . The equipment of substations is not connected to LEP 10 kW

Readiness degree -99 %.

7. The gatekeeper's office and weighing - machine's degree of the technological readiness

makes 90 %

8.The pump station water-supply system's readiness degree makes 60 %.

9. Reserve water sypply system readiness degree makes 3 %.

10. The works on laying water and industrial drains , water-supply system are now beeng conducted.

11. There are access roads to some of the objects of the factory. The territory of factory is protected by 2 m heigh concrete fence.

The characteristics of the main buildings are listed in the table. The general views of buildings are indicated on photos.

The construction of the following objects has begun:

  • Mechanical workshop (the base and part of brick walls are already built);
  • The meat canning shop;
  • Reserve water-supply tanks;
  • Administrative building.

The underground works in the main sewer station and the pump station are also done.

 

 

 

 

 

 

 