SUMMARY

        The factory is a complex of two technological shops, material and product warehouses, boilrer-room, pump station with filters and secondary objects like transformer station, cooling tower, weighing-machine, etc. JV “Tashco” is interested in additional investment or in cooperation with a companion – sponsor to finish the construction in the shortest time by the harvest season .

 The guarantee of investment is the canning factory which costs 1 587 thousand US $ according to the experts appreciation.

MARKET AND FINACIAL RISK

bulletThere are more then 60% of irrigated soil in Kilija region. That allows to grow good crops of vegetables even in dry seasons;
bulletRegional authorities are willing to create an agricultural complex including the canning factory and some most effective farms - the suppliers of early vegetables.
bulletAssortment of products is well known to the customers and is intended for the popular consumption. The trade companies from CIS, Europe are willing to buy the production of the factory.
bulletThe transportation of the production may be fulfilled by water, automobile or railway transports. The factory is situated in 500m from to Danube and in 1,5 km from Kilija sea port. The nearest railway station is Izmayil. The branch of this railway is the property of the factory.

 PRODUCT’S NOMENCLATURE

bulletCucumbers, tomatoes, squashes, paprika – tinned or pickled.
bulletTomato paste, tomato juice, sauces, ketchups.
bulletTinned green peas and corn.
bulletSquash, aubergine, pumkin caviare.
bulletStewed fruit; apple, plump, quince, apricot jams.
bulletFruit juice: with or without pulp.
bulletFruit concentrate.

THE FRUIT CANNING FACTORY DRAFT PROJECT

        The construction of next complexes was intended:

1. Fruit and vegetable canning shop draft project (capacity – 3 millions bottles a year) including:

bulletFruit – vegetable canning shop;
bulletProduct warehouse;
bulletMaterial storehouse;
bulletStorehouse for clean bottles;
bulletGatekeeper’s office with security-fire alarm system room;
bulletTransformer station;
bulletWater-supply system with two reservoirs and a pump station;
bulletPreliminary sewage filter system;
bulletRain drainage system;
bulletPump station main sewage system;

2. Tomato paste shop draft project (capacity – 4,5 million bottles a year) including:

bulletTomato paste canning shop;
bulletProducts warehouse;
bulletCirculating water supply system;
bulletCooling tower;
bulletAdministrative building;
bulletMetalworking and mechanical shop with autoclave service;
bulletCanteen for 50 people;

3. Boiler room,  sewage system draft project:

It was intended to build a boiler room with four tanks to heat the shops. It was also supposed to connect the water supply system to the city water supply system through two accumulating reservoirs and the pump station. Sewage system: everyday household and industrial sewage through the preliminary sewage filter to the main sewage system and then to the city sewage system. The transformer station with two 400 kVt electricity transformers was planed to supply electricity. The telephone connection is through the city telephone station.

The overall factory capacity is supposed to be 8,4 million bottles a year.

The area of the factory is 7,2 hectares.

The number of workers in two shops is 125 people, the overall number is 180 people.

During the harvest season the work schedule is intended to have two shifts a day. In the tomato shop – 3 shifts a day.

THE CORRECTION OF PROJECT AND COMPLETION OF CONSTRUCTION

The original project has been changed and extended in the assortment of products and in the capacity of technological lines.

The new project decision has been made:

1. In the tomato shop:

bulletIt is planed to install Yugoslavian AC – 550 line (it’s capacity is 550 ton a day) and some of the home made equipment.
bulletTo assemble a line for tomato paste packaging into barrel 200kg
bulletTo organize tomato juice “hot” bottling.
bulletMake a secondary water use system to save water at the preliminary tomato wash line.
bulletIt is planned to buy foreign equipment for aseptic tomato packaging into barrel .

2. In the fruit- vegetable canning shop:

bulletTo buy a green peas processing line and equipment for preliminary sugar corn processing.
bulletEquipment to fry vegetables for caviar processing.
bulletTo buy six more drying machines to the shop.

As the result the capacity of the factory increases from 7,5 million bottles up to 20 million bottles a year.

THE PRESENT CONDITION OF THE PROJECT

There have been built:

1. Fruit and vegetable canning shop with heat insulation, warehouse.

Inside the shop there are secondary premises, laboratories, storerooms, rooms for personal.

                    Readiness – 70%.

It is necessary to complete roofing, ventilation system, painting.

2. Tomato shop with warehouse.

            The size of the shop is 60x24 m , warehouse – 36x24 m

            Readiness – 70 %

It is necessary to complete roofing, painting, conditioning system etc.

The Hungarian tomato processing line, vacuum - steamer and tomato juice equipment are installed. The equipment is not connected up to steam, water, fruit supplying system, vacuum supplying system and electricity supply. There is no equipment for thermal tomato and juice processing and for bottling.

There are reservoirs to accumulate tomatoes, area with two barometric condensers, metal constructions for cooling tower with metal tank under it nearby the shop. In the annex there is a pump station.

  1. Material storehouse. Size - 36x14.4 m.
  2. Fruit storehouse with heat insulation. It is not equipped by cooling system.
  3. Size - 54x18 m.

  4. Boiler room without roofing . There are two boilers DE-6,5- 14-GM. It is necessary to install and connect up the secondary equipment like: conditioning system, flue, smoke stack, tanks for fuel oil etc.
  5. Readiness – 33 %.

  6. Transformer station. Two 400kVa transformers have been installed. The equipment is connected up to electric line 10 kVt.
  7. Readiness – 99%

  8. Weighing machine.
  9. Water supplying pump station, without accumulating reservoirs and pumps.
  10. Checkpoint.
  11. It has begun the construction of mechanical shop.Readiness – 8%

    There are access roads to some of the objects of the factory.

        The purpose of this survey is to inform investors and firms interested in investing financial means into the bulding canning factory. This factory is exclusively situated in a ecological pure raw zone with cheap labor and cheap raw. That is why this project rather attractive to the foreign investors.

 

 

 

 

 

 

 